I visited Siena 2 weeks back, the condition is satisfactory.
Following are salient points:
 
1. One lift fully functional....second to come up shortly (the bigger one..)
2. final painting work going on (they have started from upper floor)
3. PA and Fire fighting system installed.
4. Kitchen sink installed in few flats (again they ve started from upper floor)
5. Tile flooring done, wooden pending.
6. painting largely done, final coat remaining.
 
They have fully refined one flat on 18th floor, (I think 812) and they are showing that flat as concept as to give you a touch and feel that how ur flat will look like....in rest all flats some or the other minor work is pending....but the work is going on in a rampant way (I spend almost 2 hrs there)....If they desire they can complete the tower in 15-20 days....or max a month.
 
Thanks.
 
Sharad
Siena 311

From: Gyanendra <gyanendra.gupta@gmail.com>
To: mahagunmascot@yahoogroups.com; mascotrwa@googlegroups.com
Sent: Thursday, November 15, 2012 11:24 AM
Subject: [mahagunmascot] Re: Siena condition
 

Hi,
Could any current/future resident please share the present condition of Siena tower....I believe most of flat owners in this tower has been offered possesion.
If you have recently visited the tower/flat.....could you please share your views/inputs? (if possible a few photographs)
 
 