You have to meet mr srivastava of mahagun for reason why he again told to our contractor that GDA isnot allowing to work. Like this non of our contractor will work. It was hardly one month job but contractor has mobilize and demobilize third time.
It very difficult for me to convince him to mobilize again.
Hemant Singh
From: GD [mailto:gyanendra.dwivedi@gmail.com]
Sent: Friday, October 05, 2012 2:30 PM
To: mascotrwa@googlegroups.com
Cc: Mahagun Mascot; Singh, Hemant
Subject: Re: [RWA-Mascot:1414] Re: PNG work on hold
Dear Hemant Ji,
Last month, we saw some good progress in IGL work in the society. But, it seems again it has stopped.
Can you please update us with insider information, if any issue has encountered.
Thanks
GD
On Friday, August 24, 2012 12:01:07 PM UTC+5:30, Arun Bajpai wrote:
Dear Hemant,
As per my discussion with GD & you as well in our lase EB, Lets go to Mahagun and understand their issue. Will try to resolve this asap..
Regards,
Arun Kumar Bajpai
09999623900
Click here to report this email as spam.
Website : www.iglonline.net
----------------------------------------------------------------------------------------------
DISCLAIMER:
The contents of this e-mail and any attachment(s) are confidential
and intended for the named recipient(s) only. It shall not attach any
liability on IGL or its affiliates. Anyviews or opinions presented in this
email are solely those of the author and may not necessarily reflect
the opinions of IGL or its affiliates. Any form of reproduction,
dissemination, copying, disclosure, modification, distribution and /
or publication of this message without the prior written consent of
the author of this e-mail is strictly prohibited. If you have received
this email in error please delete it and notify the sender immediately.
Before opening any mail and attachments please check them for
viruses and defect.
No comments:
Post a Comment