Re: [RWA-Mascot:651] MAHAGUN-MASCOT POWER CUT BREAKUP

Whew.....barring 2 exceptional dates (1-05 1.6 hours and 13-05 2.9 hours), normal cuts range from 4 to 22 hours!! No wonder we are paint through our nose for power backup :(

This list should be verified against UPPCL load shedding schedule, to check if builder lobby are fooling us by forcing us to pay higher on power backup!

Thanks,
Gurpreet Singh

On Tue, May 22, 2012 at 1:55 PM, Mahagun Mascot RWA <mascotrwa@gmail.com> wrote:
Dear All,

As requested from CSK, they just forwarded me the Power Back up for the month of May 2012. Please find it and validate it and give your comment/feedback on this.

MAHAGUN-MASCOT POWER CUT BREAKUP
Sl No. Date Power Cut in Hours
1 1.05.12 1.6  
2 2.05.12 5  
3 3.05.12 6  
4 4.05.12 6.3  
5 5.05.12 4.2  
6 6.05.12 11.2  
7 7.05.12 9  
8 8.05.12 12.7  
9 9.05.12 7.9  
10 10.05.12 11.6  
11 11.05.12 7.9  
12 12.05.12 9.9  
13 13.05.12 2.9  
14 14.05.12 13.4  
15 15.05.12 10.2  
16 16.05.12 8  
17 17.05.12 8.4  
18 18.05.12 6.2  
19 19.05.12 9.9  
20 20.05.12 22  
21 21.05.12 7.9  
  TOTAL 182.2  

Regards,
Raj Kumar Raju
President, MMRWA